Improvement of energy efficiency through the renovation of the thermal installation with a high temperature aerothermal system in Hotel Alúa Village.

Location
Esquinzo, Fuerteventura
Country
Spain
Product areas
Renewable energies
Water treatment
Client
Hi Partners
Type of work
Renewable energies

Challenge

Consumption of propane gas booster for DHW generation. Need to replace a chiller plant due to its deterioration.

De un vistazo

At a glance

4,02
Simple amortization years
350.317
Emissions savings Kg Co2 / year
411
Power kw installed

What Alfa 90 did

Installation of a polyvalent thermal plant with 4 pipes for the generation of cold for the air conditioning of the hotel and medium temperature heat for the preheating of DHW and the air conditioning of the swimming pools. In addition, the boilers are replaced by two high temperature booster heat pumps for DHW generation.